Answer:
B. Portfolio B with E(R)=13% and STD=18%
Step-by-step explanation:
The computation is shown below;
Reward to risk ratio = (15% - 5%) ÷ 20% = 0.5
The porfolio should be in line i.e.
= 0.05 + 0.5 × standard deviation
For portfolio A
= 0.05 + 0.5 × 25
= 17.5%
For portfolio C
= 0.05 + 0.5 × 1
= 5.5%
Portfolio B, the std is 18%
So,
= 0.05 + 0.5 × 18%
= 14%