Answer:
Results are below.
Step-by-step explanation:
Giving the following information:
Production= 800 boxes
Each box of tile requires 0.50 hours of direct labor.
Employees of the company are paid $17 per hour.
First, we need to determine the number of hours required:
Number of hours= 800*0.5= 400 hours
Now, the total direct labor cost:
Direct labor cost= 400*17= $6,800