Answer:
8.04 ≈ 8 hours
Explanation:
Given data:
parts produced per cycle = 8
Average measured cycle time = 8.36 minutes
Average measured stress time per cycle ( observed workers time) = 4.62 minutes
e.t.c
Determine the number of standard hours the operator works
Given that the operator works for 8 hours a day and produces 380 parts
First : calculate the normal time for worker and machine ( Normal time = ( observed worker time * performance rating ) / 100
Normal time for worker = (4.62* 115) / 100 = 5.31 mins
Normal time for machine = (observed cycle time - observed worker time ) = 8.36 - 4.62 = 3.74 mins
Next; determine the Total standard time for Machine and worker = ( normal time * ( 1 + Allowance factor )
Standard Time For Worker = 5.313* (1 + 0.1) = 5.84 mins
while Standard Time for Machine = 3.74 *( 1 + 0.15) = 4.30 mins
Total standard time = 5.84 + 4.3 = 10.14 mins
Finally determine the standard hours the operator works
Standard hours = (Standard Piece Time* Pieces produced) / 60
where ; Standard piece time = Standard time / pieces per cycle = 10.14 / 8 = 1.27 mins
hence ; Standard hours = ( 1.27 * 380 ) / 60 = 8.04 hours