19.8k views
6 votes
When using the high-low method, if the high or low levels of cost do not match the high or low levels of activity, ______.

User Fedejp
by
8.5k points

1 Answer

14 votes

Answer:

Choose the periods with the highest and lowest level of activity and their associated costs.

--

Hope this Helps!

User Davisoski
by
8.2k points