Alpha Industries is considering a project with an initial cost of $9.7 million. The project will produce cash inflows of $1.67 million per year for 9 years. The project has the same risk as the firm. The firm has a pretax cost of debt of 6.12 percent and a cost of equity of 11.61 percent. The debt–equity ratio is .77 and the tax rate is 40 percent. What is the net present value of the project?

User Fubar
by
4.9k points

1 Answer

6 votes

Answer:

$660,000

Step-by-step explanation:

WACC = [wD * kD * (1 - t)] + [wE * kE]

WACC = [(0.77 / 1.77)*6.12%* (1 - 0.40)] + [(1 / 1.77)*11.61%]

WACC = 1.60% + 6.56%

WACC = 8.16%

Present value of annuity = Annuity*[1-(1+interest rate)^-time period]/rate

Present value of annuity = $1.67*[1-(1.08156745763)^-9]/0.0816

Present value of annuity = $1.67*6.206374532

Present value of annuity = $10.36 million

NPV = Present value of inflows - Present value of outflows

NPV = $10.36 million - $9.7 million

NPV = $660,000