Answer:
Budgeted labour cost = $12,180
Step-by-step explanation:
Budgeted labour cost for a forth accounting period is the product of the budgeted labour hours and the standard rate per hour.
The standard rate per hour is the amount paid to workers for each hour worked.
The budgeted labour hours is the product of budgeted production units and the standard hours per unit
Budgeted labour cost = 580× 1.5 × $14=$12,180
Budgeted labour cost = $12,180