On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,000,000 at 13% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $5,000,000, 17% bonds $3,000,000, 13% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 820,000 March 31 1,420,000 June 30 1,064,000 September 30 820,000 December 31 620,000 Required: Calculate the amount of interest capitalized for 2021 using the specific interest method.