Answer:
Hello your question has some missing data attached below is the missing data table
answer :
week 1 : C should be crashed at $5000
week 2 : C should be crashed at $5000
week 3 : F should be crashed at $12000
week 4 : F should be crashed at $15000
week 5 : P and E crashes at $20000 + $16000
Step-by-step explanation:
Normal completion time = 49 weeks
and the critical path : ( C-F-I-J-P )
Estimate the a minimum-cost crashing schedule
At week 1 : the crash ( C )activity should be at $5000 and the completion time here will be 48 weeks
At week 2 : The crash (C ) activity should be made at $5000 hence the completion time here will be 47 weeks
At week 3 : The crash ( F ) activity should be made at $12000 and the completion time will be at 46 weeks
At week 4 : The crash ( F ) activity should be made at $15000 hence the completion time will be set at 45 weeks
At week 5 : The crash activity P will be at $20000 and crash activity E will be at $16000 hence the completion time will be 44 weeks
attached below is the pictorial view of the minimum-cost crashing schedule