Choose the correct answer.

The time to complete a project varies inversely with the number of employees. If 6 people can complete the project in 4 days, how long will it take 8 people?

A. 5 days
B. 3 days
C. 2 days
D. 6 days

User Stirredo
by
5.9k points

2 Answers

12 votes
if 6 complete that in 4 days then 1 man completes it in 24 days. So 8 men would complete the work in 3 days.
User Paul Gerarts
by
5.2k points
3 votes
Answer is option c which is 2 days