77,653 views
1 vote
1 vote
It takes courage to kill a project, but sometimes you know it has to be done. Some common symptoms of a failing project are ill-defined initial requirements, constant changes in scope, excessive changes in resources and personnel, and extreme stress/tension over anticipated changes. Yet, a project may have followed the "book" and done everything right, but still need to be terminated. This was the case with a project in the U.K. where the client was highly committed to the project, contributing time, resources, and prompt decisions. The scope was clear, completion criteria agreed upon, the budget and timeframe acceptable to all. Early on, however, an unavoidable scope change had to be made, requiring a 20 percent increase in time and a 10 percent increase in cost, agreed to by the client. As the project approached the end of the fi rst phase, it was clear that the quality and schedule were both deteriorating, as indicated in progress reports to both the client and senior management. A quick review showed that the results were not going to be acceptable. With the agreement of the PM, an outside Expert was called in to review the effort to date and make a recommendation. Then a joint meeting was held with the Expert, the PM, the Program Manager, and the primary contractor where it was decided that the best thing to do was to work together to complete phase one and then terminate the project, with a clean handover to another team to tackle phase two. Although disappointing to everyone, the close and frequent communications of both progress and concerns throughout the project with upper management and the client, offered in timely, digestible amounts, reduced their expectations and protected the client from a surprise at the end. Honest, consistent communication throughout the project life cycle resulted in improved trust, integrity, and confi dence in the vendor and their team.

Required:
a. What are your thoughts about doing everything right and the project still failing?
b. Does the admonition "Never surprise the boss!" now make more sense? Why?
c. Do you think the scope change at the beginning was the problem here, or was there going to be a problem anyway?

User Qeatzy
by
3.5k points

1 Answer

4 votes
4 votes

Solution :

a). There are several methodologies for the projects that are followed by the different companies. The successful of any project depends upon the far sightedness of the project manager and the ability of him to the execute the project in a proper order. One of the key factors that makes a project complete is the behavior of the people.

The vendors incur some excessive or some unnecessary costs to the project of they are not properly managed. The duty of the project manager is to foresee the scope of change if there is any.

If there were some additional cost and additional time for the completion of the project, then it means that it will delay the benefits of the project to others and hence attracts lower return of investments. Even though everything went according to the papers or the book, there is a lack of dedication on the project manager who believed and trusted the vendor too much.

b). A manager needs complete and clear information for an effective decision making. In any project, surprises gives a lesser amount of time and also less information related tot he project to resolve any issues that occurs at any time. It also disappoints the management that leads to spur of moment decision. So, 'Never surprise he Boss' makes a complete sentence.

c). The major factor why the project failed is the changed in the scope. The objectives are poorly cited and the timelines went overhead including the cost of the project. Too much trust of the project manager on the vendor also lead to the schedule and the quality issues.

User Trivektor
by
3.0k points