Answer:
Results are below.
Step-by-step explanation:
To calculate the direct material price and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (2.1 - 2)*14,850
Direct material price variance= $1,485 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (7.9*1,500 - 14,850)*2.1
Direct material quantity variance= $6,300 unfavorable
To calculate the direct labor efficiency and rate variance, we need to use the following formulas:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (1,500*0.5 - 600)*5
Direct labor time (efficiency) variance= $750 favorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (5 - 7)*600
Direct labor rate variance= $1,200 unfavorable
Actual rate= 4,200/600= $7