Answer:
See below
Step-by-step explanation:
The preparation of direct labor cost budget for March is seen below;
Particulars Foaming department Assembly department
Production 8,100 units 19,500 units
Hours required
Junior 2,025 4,050
Hours required
Pro 5,850 13,650
Total hours
Department Wise (A) 7,875 17,700
Total Hourly rate (B) $17 $19
Total direct labor cost (A × B) $133,875 $336,300
••Workings
For Junior, it would be :
Foaming
= 0.25 hour per unit × 8,100 units
= 2,025
Assembly
= 0.50 hour per unit × 8,100 units
= 4,050
For Pro, it would be:
Foaming
= 0.30 hour per unit × 19,500 units
= 5,850
Assembly
= 0.70 hour per unit × 19,500 units
= 13,650