Answer:
$11.40
Step-by-step explanation:
Calculation to determine the unit cost which Forever Ready Company should not go in bidding on the government contract
FOREVER READY COMPANY UNIT COST
Direct materials $7.75
($225,100/29,040)
Direct labor $2.85
($82,800/ 29,040)
Variable factory overhead $0.80
($23,156/ 29,040)
Total Per unit cost $11.40
($7.75+$2.85+$0.80)
Therefore the unit cost which Forever Ready Company should not go in bidding on the government contract is $11.40