Amy and Builders Corporation enter into a contract in which Amy agrees to deliver cement to Builders at a construction site. They neglect to include a price in the agreement. A court will a. determine a reasonable price for the cement and insert it into the contract. b. leave the parties in the position in which it found them. c. refuse to enforce the agreement. d. select the lowest quoted price for cement and insert it into the contract.

1 Answer

5 votes

Answer:

a. determine a reasonable price for the cement and insert it into the contract.

Step-by-step explanation:

Since in the question it is mentioned that the amy & builders corporation would entered into a contract where amy agrees to deliver the cement at the construction site. At the same time they deny to include the price in the agreement. So here the court would say that calculate the price for the cement and the same would be involved in the contract as without price the contract is not valid

Hence, the option a is correct