Answer:
Requirement: Determine the overhead rate for each activity "Materials handling, Machine setups, Quality inspections"
Materials handling overhead rate = Total cost / Cost driver volume
Materials handling overhead rate = $30,000 / 1,000
Materials handling overhead rate = $30
Machine setups overhead rate = Total cost / Cost driver volume
Machine setups overhead rate = $23,750 / 475
Machine setups overhead rate = $50
Quality inspections overhead rate = Total cost / Cost driver volume
Quality inspections overhead rate = $19,000 / 475
Quality inspections overhead rate = $40