if 15 workers complete a piece of work in 18 days in how many days will 27 workers complete the same work?​

User Joozek
by
6.4k points

1 Answer

2 votes

10 days is your answer

Answer:

15 workers =18 days to complete work

1 worker =18×15=270 days to complete work

27 worker=270/27=10 days to complete work