154k views
2 votes
Winsor Construction Company uses the percentage-of-completion method of accounting. In 2007, Winsor began work on a contract it had received which provided for a contract price of $7,500,000. Other details follow: 2007 Costs incurred during the year $3,600,000 Estimated costs to complete as of December 31 2,400,000 Billings during the year 3,300,000 Collections during the year 1,950,000 What should be the gross profit recognized in 2007?

User Giusy
by
3.0k points

1 Answer

4 votes

Answer:

The gross profit recognized in 2007 is $1,200,000

Step-by-step explanation:

Use the following formula to the percentage of completion

Percentage of completion = Total Cost / Contract price

Total cost = Cost incurred to date + Estimated cost to complete = $3,600,000 + $2,400,000 = $6,000,000

Contract price = $7,500,000

Placing values in the formula

Percentage of completion = $6,000,000 / $7,500,000 = 0..80 = 80%

Use the following formula to calculate the gross profit

Gross profit = Contract price - Total Cost = $7,500,000 - $6,000,000 = $1,500,000

Now calculate the gross profit recognised as follow

Gross profit recognised = Gross profit x Percentage of completion = $1,500,000 x 80% = $1,200,000

User Patrick Altman
by
3.4k points