The amount of materials to be purchased during the budget period is equal to budgeted: A. total production needs plus units in the beginning materials inventory minus the units in the ending materials inventory. B. total production needs plus units in the ending materials inventory minus the units in the beginning materials inventory. C. units to be produced plus units in the beginning materials inventory minus the units in the ending materials inventory. D. units to be produced plus units in the ending materials inventory minus the units in the beginning materials inventory.

1 Answer

3 votes

Answer:

. B). total production needs plus units in the ending materials inventory minus the units in the beginning materials inventory.

Step-by-step explanation:

The budget period can be regarded as

period of time whereby one has the authority to spend the awarded funds in a way that meet the matching as well as the cost-sharing requirement. It should be noted that the amount of materials to be purchased during the budget period is equal to budgeted total production needs plus units in the ending materials inventory minus the units in the beginning materials inventory.

User Lanbo
by
4.2k points