Answer:
Direct labor rate variance= $482 favorable
Step-by-step explanation:
Giving the following information:
Variable overhead 0.5 hours $ 7.30 per hour
Actual direct labor hours= 2,410
The actual variable overhead rate was $7.10 per hour.
To calculate the variable overhead rate variance, we need to use the following formula:
Variable manufacturing overhead rate variance= (standard rate - actual rate)* actual quantity
Variable manufacturing overhead rate variance= (7.3 - 7.1)*2,410
Variable manufacturing overhead rate variance= $482 favorable