Answer:
c. This is a good project if the probability of expropriation is smaller than 0.5
Step-by-step explanation:
initial outlay = $8,000,000
if no expropriation, NPV = -$8,000,000 + $1,500,000/0.12 = $4,500,000
if the risk of expropriation is 0.33:
NPV = $925,211
if the risk of expropriation is 0.5:
NPV = -$425,265
the breakeven risk = 44.6%