Answer:
the materials quantity variance for April is $2,552 unfavorable
Step-by-step explanation:
The computation of the materials quantity variance for April is shown below:
= (standard quantity - actual quantity) × standard rate
= (4,300 units × 8.4 liters - 37,000 liters) × $2.90
= (36,120 liters - 37,000 liters) × $2.90
= 880 liters × $2.90
= $2,552 unfavorable
hence, the materials quantity variance for April is $2,552 unfavorable
The same is followed