Brown Corporation uses a job-order costing system with a single plant-wide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 40,000 Total fixed manufacturing overhead cost $344,000 Variable manufacturing overhead per machine-hour $3.9 Recently, Job M759 was completed. It required 60 machine-hours. The amount of overhead applied to Job M759 is closest to: (Round your intermediate calculations to 2 decimal places).

User Ankit Soni
by
8.1k points

1 Answer

6 votes

Answer:

See below

Step-by-step explanation:

With regards to the above, first we need to compute the fixed manufacturing overhead.

Fixed manufacturing overhead

= Total fixed manufacturing overhead ÷ Total machine hours

= $344,000 ÷ 40,000

= $8.6 per machine hour

Calculation of overhead applied to Job M759

Variable manufacturing overhead

= 60 machine hours × $3.9

= $234

Fixed manufacturing overhead

= 60 machine hours × $8.6

= $516

Therefore, total overhead applied to job M759 is $750

User Sam Janssens
by
8.5k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories