Answer:
A. 12.3%
B. 68%
Step-by-step explanation:
a.Calculation to determine the required return for the project
Required return=(0.62/1.62*5.7%)+(1/1.62*13.2%)+2%
Required return=0.022+0.081+2%
Required return=0.124*100
Required return=12.3%
Therefore the required return for the project will be 12.3%
b. Calculation to determine the maximum cost the company would be willing to pay for this project
Maximum cost =6.3/(12.3%-3%)
Maximum cost =6.3/9.3%
Maximum cost =0.67.7*100
Maximum cost =67.7%
Maximum cost=68% (Approximately)
Therefore the maximum cost the company would be willing to pay for this project will be 68%