38.6k views
24 votes
It takes 12 men 5 days to complete a job.

(a) Work out how many days it would take 3 men to complete the same job.

I know that the answer is 20 but I need an explanation​

1 Answer

7 votes
12 men, 5 days.
If you divide the amount of laborers by 4, you must multiply the time it takes by 4. Thus 12/4=3 men and 5*4= 20 days.
User Migwell
by
7.8k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories