The master budget of Sheridan Company shows that the planned activity level for next year is expected to be 50000 machine hours. At this level of activity, the following manufacturing overhead costs are expected: Indirect labor $720000 Machine supplies 180000 Indirect materials 150000 Depreciation on factory building 90000 Total manufacturing overhead $1140000 A flexible budget for a level of activity of 60000 machine hours would show total manufacturing overhead costs of

1 Answer

7 votes

Answer:

$1,350,000

Step-by-step explanation:

Calculation to determine the total manufacturing overhead costs

First step is to calculate the Variable overhead

Variable overhead= $720,000 + $180,000 +$150,000

Variable overhead=$1,050,000

Second step is to calculate Unitary variable overhead

Unitary variable overhead= $1,050,000/50,000

Unitary variable overhead= 21

Now let calculate the total manufacturing overhead costs

For 60,000 units:

Total Manufacturing Overhead Costs = 21*60,000 + 90,000

Total Manufacturing Overhead Costs= $1,350,000

Therefore the total manufacturing overhead costs is $1,350,000