Answer: $97,421,041
Step-by-step explanation:
Cost for the facility in 2012 = $70 million
Construction Cost Index in 2012 = 8802
Construction Cost Index today = 12250
The estimated cost of the facility today will be:
= Cost of facility in 2012 × (CCI today / CCI in 2012)
= 70,000,000 × 12250/8802
= $97,421,041