Answer: $14.5 million
Step-by-step explanation:
The following information can be gotten from the question;
Total equipment cost = $4.2 million
Direct cost factor = 1.52
Indirect cos factor = 0.37
The total plant cost will then be calculated as:
= 4.2 × (1 + 1.52) × (1 + 0.37)
= 4.2 × 2.52 × 1.37
= 14.5
Therefore, the total plant cost is $14.5 million