132k views
4 votes
Which one of the following statements is​ false? A. The activities along the critical path determine the completion time of the project. B. If one of the activities on the critical path is​ delayed, the entire project will be delayed. C. There may be more than one critical path in a project network. D. The critical path is the sequence of activities between a​ project's start and finish that takes the shortest time to complete.

User Owen Chen
by
3.7k points

1 Answer

4 votes

Answer:

C.

Step-by-step explanation:

The critical path is the sequence of activities between a​ project's start and finish that takes the shortest time to complete.

User Blerta
by
4.4k points