132k views
4 votes
Which one of the following statements is​ false? A. The activities along the critical path determine the completion time of the project. B. If one of the activities on the critical path is​ delayed, the entire project will be delayed. C. There may be more than one critical path in a project network. D. The critical path is the sequence of activities between a​ project's start and finish that takes the shortest time to complete.

User Owen Chen
by
8.2k points

1 Answer

4 votes

Answer:

C.

Step-by-step explanation:

The critical path is the sequence of activities between a​ project's start and finish that takes the shortest time to complete.

User Blerta
by
8.3k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories