Answer:
Pinacle Corp.
Pinacle's plantwide factory overhead rate for the current year is:
= $7 per machine hour.
Step-by-step explanation:
a) Data and Calculations:
Budgeted overhead cost for the current year = $350,000
Actual overhead costs for the year = $325,000
Plantwide allocation base, machine hours = 50,000
Actual machine hours = 40,000
Budgeted production units = 10,000
Actual production units = 9,800
The plantwide factory overhead rate for the current year is:
= Budgeted overhead cost/Budgeted machine hours
= $350,000/50,000 = $7 per machine hour
Allocated overhead = 40,000 * $7 = $280,000
Under-absorbed overhead = $45,000 ($325,000 - $280,000)