Answer:
16days
Explanation:
This is an inverse proportionality
Let the number of men be m
Let the time taken in days be d
Hence m ∝ 1/d
m = k/d
If 8 men can complete the project in 24 days, then;
8 = k/24
k = 8*24
k = 192
To determine the time it will take 12 men to complete the same job, we will say;
m = k/d
12 = 192/d
d = 192/12
d = 16
Hence it will take 12men 16days to finish the same job