5) Explain the difference between value analysis and value engineering.

User Olrac
by
8.3k points

1 Answer

4 votes

Answer:

As cost avoidance or cost reduction before manufacturing, value engineering is strongly related to target costing. Value analysis is the process of avoiding or reducing the cost of a product that is already in production.