Answer:
1. a. 117.
2. $2,051.48
3. 592.82
4. 1472.01
5. d. 4116.11
6. d. 24
Explanation:
Economic Order Quantity :
Economic order quantity is
EOQ = 117
2. ordering cost :
( total demand / EOQ ) * Ordering cost
( 600 / 117 ) * 400 = $2051.28
3. Holding cost :
Total demand * holding cost per unit
= 592.82
Reorder Point = Daily Demand * lead time
Reorder point = 600 / 350 * 14 = 24