Answer:
Results are below.
Step-by-step explanation:
To calculate the direct material price and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (5 - 2.1)*56,100
Direct material price variance= $169,690 favorabe
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (8,840*4 - 36,450)*5
Direct material quantity variance= $5,450 unfavorable
To calculate the direct labor efficiency and rate variance, we need to use the following formulas:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (1.5*8,840 - 18,000)*10
Direct labor time (efficiency) variance= $47,400 unfavorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (10 - 8.2)*18,000
Direct labor rate variance= $32,400 favorable