Answer:
Parts management= $630 per part
Step-by-step explanation:
Giving the following information:
Activity Estimated Overhead Cost Estimated Activity Automated Assembly $189,000 7,000 machine hours
Parts management $63,000 100 part numbers
To calculate the activity rate, we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Parts management = 63,000 / 100