Answer:
$34,286
Step-by-step explanation:
Step 1
Total number of employees :
Maintenance 2
Department A 8
Department B 4
Total 14
Step 2
Allocation to Department B :
Department B = 4 / 14 x $120,000
= $34,286
Conclusion :
Accounting Department's cost allocated to Department B using the direct method is $34,286