Answer:
$14,853.84
Step-by-step explanation:
Calculation to determine How much overhead cost would be assigned to Product V91Z using the activity-based costing system
Overhead cost assigned to Product V91Z
Assembly product $6,956.23
($14.11*493)
Processing customer order $1,667.61
($79.41*21)
Setting up batches $6,230
($89*70)
Total $14,853.84
Therefore How much overhead cost would be assigned to Product V91Z using the activity-based costing system will be $14,853.84