All of the machine hours take place in the Fabrication department, which has an estimated overhead of $84,000. All of the labor hours take place in the Assembly department, which has an estimated total overhead of $72,000. The Ramapo Company uses a single overhead rate to apply all overhead costs. What would the single plantwide rate be if it was based on machine hours instead of labor hours

User Kenesia
by
4.8k points

1 Answer

7 votes

Answer:

Results are below.

Step-by-step explanation:

We weren't provided with the number of machine-hours. To guide an answer, I will assume that 35,000 machine hours were estimated in the Fabrication Department.

To calculate the predetermined manufacturing overhead rate we need to use the following formula:

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Predetermined manufacturing overhead rate= 84,000 / 35,000

Predetermined manufacturing overhead rate= $2.4 per machine hour