Answer:
80%.
Step-by-step explanation:
Question didn't state what is being looked for, but then....
Weight of the box, w = 100 N.
Length of the plane, L = 5 m
Force used, = 75 N
Length pushed through, = 3 m
Looking at the stated parameters, the first thing that comes to mind is to look or calculate for the efficiency of the machine.
Tha efficiency can be gotten by using the relation
Change in energy divided by work done. This is gotten by saying
(100 * 3) / (5 * 75) =
300/ 375 = 0.8
Therefore, the efficiency of the machine has been calculated to be 80% or 0.8