Answer:
Yes I would
Step-by-step explanation:
We have these costs
Variable cost:
Materials = 600 dollars for each of component.
Labour is at a rate of 150 dollars each
For fixed cost depreciation = 300 dollars
Now we have to calculate the average variable cost
Cost of production of 1 pc + labour price of 1
= 600 + 150
AVC = 750
The sales price for each of the 10000 pc = 800 dollars
Now we can see that price p is greater than or equal to avc. 800 >=750
So the I have to accept to produce these pcs at the rate of 800 for 1 pc.
800-750 = 50
50x10000 = $500000 from the sale of the 10000 pcs