Answer:
17.5minutes
Step-by-step explanation:
Calculation to determine would be the information turnaround time for a defect made at station 2
Station 2 information turnaround time=[(Station 9-Station 2)*2.50 minutes/unit]
Station 2 information turnaround time=7x 2.50
Station 2 information turnaround time=17.5minutes
Therefore the information turnaround time for a defect made at station 2 is 17.5minutes