Your plan projects revenue of $5,000, $8,000, and $10,000 in years 1 through 3. Expenses are projected to be $9,000 for each of years 1 through 3. If your only funding need is the gap between revenue and expenses, which is the best estimate of your maximum cumulative funding need?.

1 Answer

7 votes
Step-by-step explanation:
The only funding needed is the difference between revenue and expense.
For year 1: funding required is $9,000 -$5000 = $4000
For year 2: funding required is$ 9,000 - $8000 = $1000
For year 3: funding required is $9000 -$10,000 = -$1000
cumulative funding = $4000, + $1000 + (-$1000)
=$5000 - $1000
=$4000