Answer:
Kentucky Lumber and MillWork Company Vs Rommell Company
Most likely, the court will decide that Kentucky should continue to perform its contract obligations. We note that following the destruction of the mill by fire, Kentucky never invoked the clause of force majeure. It continued to fulfill its obligations for a period of two months.
Before the case comes to the court, Kentucky should have requested for a renegotiation of the contract price with Rommell if it had discovered that the cost of buying from third-party suppliers could prevent it from continuing with the contract. Note that the fulfilment of a contract is not based on mere wishes but on facts, supported by the prevailing circumstances.
Step-by-step explanation:
The court will decide to answer Rommell's prayers for an equitable relief by forcing Kentucky Mill to continue with the specific performance of the contract or to pay damages to Rommell for losses arising from the failure of Kentucky to fulfil the contract.