Answer: 12
Step-by-step explanation:
The level of safety stock that would give a reorder point of 60 units goes thus:
Firstly, we should note that the formula that'll be used in calculating the reorder point will be:
= dxL + Safety stock
where,
Reorder point = 60
dxL = (2000/250) x 6 = 48
Safety stock = Unknown
We then put the values gotten into the formula which will be:
Reorder point = dxL + Safety stock
60 = 48 + safety stock
Safety stock = 60 - 48
Safety stock = 12 units