Answer:
Step-by-step explanation:
Relevant costs are the costs which are affected by the decisions made by the management of an organization while irrelevant costs do not change in future as they're not affected by the decisions from the management.
Based on the information given, the relevant cost are:
1. Power cost
2. Inspection cost
The non relevant cost are:
1. Supplies cost
2. Assembly cost