A project can be completed by 5 workers in 24 days. How many workers are needed to finish the project in 15 days? The time to complete a project is inversely proportional to number of people who are doing the project.

User Ruelluna
by
7.9k points

1 Answer

2 votes

8

Explanation:

5×4 equals 120 120 divided by 15 equals 8 which is the answer