Answer:
$371,650
Step-by-step explanation:
Use the costs formula provided to find the flexed manufacturing overhead cost for March.
A flexed budget amount is a budgeted amount adjusted to actual level of activities as follows.
Actual Activity is given as 6,150 machine-hours
Manufacturing overhead cost = $45,700 + $53 x 6,150 machine-hours
= $371,650
Therefore,
The manufacturing overhead in the flexible budget for March would be closest $371,650