Answer:
a) 84,000 units ( materials )
82,000 units ( conversion )
b) $6.5
c) $494,000 ( material )
$494,000 ( conversion )
Step-by-step explanation:
a) Calculate the equivalent unit of production
applying the weighted average method
for the units completed and transferred out
= 5000 + 79000 - 8000 = 76000 ( material ) , Conversion = 76000
For ending work in process
= 8000 ( material ) , conversion = 8000 * 75% = 6000
∴ equivalent units of production
= 76000 + 8000 = 84,000 units ( materials )
and
= 76000 + 6000 = 82,000 units ( conversion )
B) calculate the unit production costs
Total cost incurred till date = beginning work in process + current period cost
= 30,000 + 390,000 = 420,000 ( material )
(conversion) = 123,000.
Equivalent units = 84,000 ( materials ) , 82,000 ( conversion )
cost per unit = 420,000 / 84000 , 123000/ 82,000
= 5 , 1.5
Hence Total unit cost = $6.5 ( i.e. 1.5 + 5 )
C) cost to be assigned
76000 * 6.5 = $494,000 ( material )
76000 * 6.5 = $494,000 ( conversion )