Answer and Explanation:
The computation of the variance is shown below;
a) Material price variance is
= (Standard price - actual price) × actual quantity
= ($1.5 - $1.48) × 25000
= $500 F
b. Material quantity variance is
= (Standard quantity - actual quantity) × Standard price
= (3000 × 6 - 20,000) × 1.5
= $3,000 U
c) Labor rate variance is
= (Standard rate - actual rate) × actual hours
= ($21 × 4000 - $88,000)
= $4,000 U
d. Labor efficiency variance is
= (Standard hour - actual hour) × Standard rate
= (3000 × 1.3 - 4000) × 21
= $2,100 U