Answer and Explanation:
The preparation of the direct labor cost budget for July month is as follows:
Particulars Forming Dept Assembly Dept
Production 7,400 units 18,600 units
Hours required junior 1,480 2,960
(7,400 units × 0.2) (7,400 units × 0.4)
Hours required pro 6,510 13,020
(18,600 units × 0.35) (18,600 units × 0.7)
Total hours 7,990 15,980
Total hours rate $14 $12
Total direct labor cost $111,860 $191,760