In July, a new endoscopy and electrophysiological lab are opening up. It is projected 60 endoscopies and 5 EP studies will be performed daily. Based on preliminary work sampling to determine the time it will take to code these types of cases; it will take 5 minutes per endoscopy and 15 minutes per EP study. Calculate number of FTE needed to be hired to cover additional procedures per 7.5 hour day

User Prashanth Benny
by
3.0k points

1 Answer

5 votes
5 votes

Answer:

The number of FTE needed to be hired to cover the additional procedures per 7.5 day work is:

= 1.

Explanation:

a) Data and Calculations:

Endoscopies EP Studies Total

Projected number of studies 60 5 65

Time in minutes for per study 5 15

Total time required (in minutes) 300 75 375

Full-time Employee (FTE) works 7.5-hour day or 450 minutes (7.5 * 60) per day.

b)The number of full-time employees (FTE) needed to be hired to cover the additional procedures per 7.5-day work is 1. The FTE has 450 minutes available for the additional procedures. She will only require 375 minutes. Therefore, she has extra (idle) time of 75 (450 - 375) minutes per workday.